Cidade de Paraty Lifeboat Davit Installation

Project at a Glance

Client: SBM Offshore Brazil

Location: FPSO Cidade de Paraty, Brazil

Scope: Installation of two additional lifeboat davits

Equipment: Custom double-boom lifting system, temporary lifting structures, winches and wire rope systems

Lifting Capacity: 6.4 tonnes per davit

Services: Engineering, structural verification, heavy lifting and rope access

A Custom Lifting Solution for a Challenging Offshore Installation

SBM Offshore Brazil required the installation of two additional lifeboat davits on the port and starboard sides of FPSO Cidade de Paraty. With each davit weighing approximately 6.4 tonnes, the installation presented several challenges due to the highly congested working environment and limited available deck space.

The davits had to be transferred from a supply vessel to the FPSO, requiring a complex floating-to-floating lifting operation. The required lifting distance and lack of a suitable permanent lifting solution meant that a custom lifting system had to be developed.

Conbit was engaged to engineer and execute a complete lifting methodology tailored to the specific conditions onboard the FPSO.

Engineering a Custom Double-Boom Lifting System

To overcome the installation challenges, Conbit designed and implemented a custom double-boom lifting system. The temporary lifting structure enabled the davits to be safely transferred from the supply vessel and positioned at their final locations on the FPSO.

The scope included engineering, structural verification, the design and installation of temporary lifting structures, detailed lifting procedures and offshore execution. Winches, wire rope systems, support frames and dedicated rigging arrangements were integrated into the solution to ensure precise control throughout the operation.

Rope access techniques were also incorporated to support installation activities in areas with restricted accessibility, reducing the need for conventional access equipment in the congested working environment.

‍

Watch how we prepare and execute

Watch how we prepare and execute

Rope Access Technicians installing modular lifting system on FPSO with ocean in the background

Managing Complex Offshore Conditions

The floating-to-floating nature of the operation required careful consideration of vessel movements, environmental conditions and the available working space. The long-boom configuration made accurate planning and coordination essential to maintain control during the transfer and positioning of the davits.

Additional challenges arose during welding and interface activities between the davits and their supporting structures. Close cooperation between Conbit and SBM Offshore Brazil was essential to coordinate the various activities, maintain quality standards and address operational challenges throughout the campaign.

Successful Installation

Both lifeboat davits were successfully installed at their designated positions onboard FPSO Cidade de Paraty. Despite operational delays and challenges during execution, the project was completed to the satisfaction of the client.

The project demonstrates Conbit's ability to engineer and execute complex offshore lifting operations in highly restricted environments. By combining specialised engineering, temporary lifting structures, rope access techniques and heavy lifting expertise, Conbit delivered an integrated solution for a challenging offshore installation.

The developed methodology also provides a proven approach that can be applied to future lifeboat davit installation and replacement projects on FPSOs and other offshore facilities.

‍

See how we got to work

Bas frame of modular lifting system on FPSO
Lifeboat davit being manoeuvred into position with modular lifting systemn with
Lifeboat suspended in air by modular lifting system after retrieval from vessel

PRoject case study pdf

Download the PDF of this project case study here.

Thanks for leaving your email address. You can now download the requested case study

Download Case study
Oops! Something went wrong while submitting the form.
No items found.

Whitepaper

Download our whitepaper of this case.

Download whitepaper

Related Cases

Related Services

Maritime
Oil & Gas
Petrochemical
Wind

Lifeboat Davit Installation Services

Onshore & Offshore
Oil & Gas
Petrochemical
Wind
Maritime

Living Quarter Installation Services

Onshore & Offshore
Oil & Gas
Petrochemical
Wind
Maritime

Caisson Replacement Services

Onshore & Offshore
Maritime
Oil & Gas
Petrochemical

Crane Replacement Services

Onshore & Offshore
Oil & Gas
Petrochemical

Flare Tip Replacement Services

Onshore & Offshore
Maritime
Wind
Oil & Gas

Inspections

Onshore & Offshore
Oil & Gas
Petrochemical
Wind

Modification

Onshore & Offshore
Oil & Gas
Petrochemical
Wind

Maintenance

Onshore & Offshore
Oil & Gas
Wind
Petrochemical
Maritime

Installation

Onshore & Offshore
Oil & Gas
Petrochemical

Decommissioning

Onshore & Offshore

Contact

We're here to answer your questions

Do you have any technical questions, general enquiries or do you need additional information? Don’t hesitate to contact our experts. With their expertise and experience in lifting services, they will gladly help you.

You can contact us by phone or email. We’re looking forward to your questions!
Jasper Horsten

Jasper Horsten

Sales Manager Americas / Offshore wind