Cassia-A Vent Boom Removal

Project Overview

For Massy Wood and BP, Conbit was involved in the planned removal of the inclined vent boom on the Cassia-A platform in Trinidad and Tobago. The scope required the boom to be removed in two or three sections, lowered onto a supply vessel, and subsequently disposed of.

Due to the inclined geometry of the boom, limited access on the platform, and the offshore handling requirements, a tailored lifting solution was required. Conbit was asked to develop a safe and practical lifting method that could be prepared within a tight project schedule.

The Challenge

The removal of the inclined vent boom presented several challenges. The boom had to be divided into separate sections and transferred safely from the platform to a supply vessel, while working within the limitations of the existing platform infrastructure.

In addition, the project schedule required several new items of equipment to be designed, fabricated, and tested within a short time frame. One of the key developments was a dedicated installation tool for the SL900.

As the SL900 would eventually extend beyond the reach of the platform crane during assembly, a solution was needed to allow the system to continue building up independently. This required the development of a dedicated tool to support the installation process.

‍

Watch how we prepare and execute

Watch how we prepare and execute

The Solution

During the concept phase, Conbit developed two lifting solutions for the Cassia-A vent boom removal.

The first concept combined the SL500 with a gantry arrangement. The second concept was based on Conbit's SL900 modular lifting system. Following an evaluation of both options, the client selected the SL900as the preferred solution.

The lifting system was designed around the SL900, supportedby 15 mt hydraulic winches for controlled handling of the boom sections. The selected solution provided a suitable approach for handling the inclined structure while working within the access and crane limitations of the Cassia-A platform.

This represented an important milestone for Conbit, as it was the first project in which the SL900 was selected for execution.

SL900 Installation Tool

A dedicated installation tool was developed specifically to support the build-up of the SL900. Part of the assembly would take place outside the reach of the platform crane once the system reached a certain height. The installation tool was therefore designed to allow the SL900 to continue building up independently.

Due to the tight project schedule, the tool had to be designed, fabricated, and tested within a short timeframe. Conbit successfully completed the development and testing, providing an important step towards the concept of a self-building lifting structure for future offshore applications.

Development & Testing

The project required close coordination between engineering, fabrication, and testing activities. With several components still under development, Conbit had to move quickly from design to fabrication and testing.

An extended Factory Acceptance Test (FAT) was conducted with Massy Wood representatives present at Conbit. This provided an opportunity for both teams to work closely together, resolve technical topics efficiently, and gain practical experience with the proposed system and installation method.

Evaluation

Although the Cassia-A project was stopped after completion of the FAT, the project provided valuable experience for the further development of the SL900.

The close cooperation during the extended FAT resulted in important practical feedback on the system, its installation method, and the supporting equipment required for offshore deployment. The development and successful testing of the dedicated installation tool was particularly valuable, demonstrating how the SL900 can be built up independently when conventional crane access is no longer available.

The project therefore contributed to the continued development and offshore readiness of the SL900, while strengthening Conbit's experience in developing engineered lifting solutions for challenging offshore environments.

‍

See how we got to work

Rope acces technician finishing tilt head installation on the SL900
Bas frame of the SL900 with the specially designed installation tool
Load test on the Conbit yard with the SL900
SL900 build up with specially designed installation tool by rope access technicians

PRoject case study pdf

Download the PDF of this project case study here.

Thanks for leaving your email address. You can now download the requested case study

Download Case study
Oops! Something went wrong while submitting the form.
No items found.

Whitepaper

Download our whitepaper of this case.

Download whitepaper

Related Cases

Related Services

Maritime
Oil & Gas
Petrochemical
Wind

Lifeboat Davit Installation Services

Onshore & Offshore
Oil & Gas
Petrochemical
Wind
Maritime

Living Quarter Installation Services

Onshore & Offshore
Oil & Gas
Petrochemical
Wind
Maritime

Caisson Replacement Services

Onshore & Offshore
Maritime
Oil & Gas
Petrochemical

Crane Replacement Services

Onshore & Offshore
Oil & Gas
Petrochemical

Flare Tip Replacement Services

Onshore & Offshore
Maritime
Wind
Oil & Gas

Inspections

Onshore & Offshore
Oil & Gas
Petrochemical
Wind

Modification

Onshore & Offshore
Oil & Gas
Petrochemical
Wind

Maintenance

Onshore & Offshore
Oil & Gas
Wind
Petrochemical
Maritime

Installation

Onshore & Offshore
Oil & Gas
Petrochemical

Decommissioning

Onshore & Offshore

Contact

We're here to answer your questions

Do you have any technical questions, general enquiries or do you need additional information? Don’t hesitate to contact our experts. With their expertise and experience in lifting services, they will gladly help you.

You can contact us by phone or email. We’re looking forward to your questions!
Jasper Horsten

Jasper Horsten

Sales Manager Americas / Offshore wind